Giao Long Paper Factory - Stage 2

Giao Long Paper Factory - Stage 2

Project Description

Location
Giao Long Industrial Zone - Ben Tre
Investors
Dong Hai Joint Stock Company
Type
産業・製造
Scope of work
Constructing foundation, structure and finishing works
Scale
18.000m2 
Year
2016
Estimated Time of Completion
24/09/2017
Progress
85%

Project Description

The project was built with the goal of changing the manufacturing capacity from 600 tons / day (with a total investment of approximately 660 billion VND) to 660 tons / day (with a total investment capital is raised about 720 billion) in order to help DOHACO increase competitiveness in the market.